1. You try to add a dependency and AWRA refuses it, citing a cycle. What is the right response?
2. Two tasks are late. Task A has zero slack; Task B has four days of slack. Which should you protect first?
3. A task has no start or due date. How does it appear on the Gantt timeline?
4. What does setting a baseline do?
5. How is the critical path determined?