1. What does supplier lead time include?
2. How should you measure real lead time?
3. A supplier promises 5 days but your POs averaged 7.3. Which should you plan on?
4. At 20 units/day and a 7.3-day lead time, the reorder point is roughly:
5. Why does wider lead-time variability demand more safety stock?