Where the Buying Money Went
A board asks three questions about buying: who gets our money, how long does it take, and what did tendering save. Procurement spend analytics answers all three from the purchase orders themselves, in one currency at a time, and says how many orders each answer rests on.
The finance committee of a juice and bottled-water processor in Namanve, outside Kampala, meets on the last Thursday of the quarter. This time the chair has written three questions on the agenda in advance. How much of our buying goes to our top five suppliers? Why does it take a month to get a spare part? And the procurement team says the new tender process saves money: how much, and compared with what? The procurement manager has a week. She has 312 purchase orders for the year so far, most in shillings and a dozen in dollars for imported caps and labels, and an export from last year’s attempt that took two people four days.
None of those questions is hard to ask, and every one of them is usually answered from a spreadsheet built for the meeting and thrown away after it. The data is already in the purchase orders. What is missing is a view that reads them the same way every time, so the answer in March can be compared with the answer in June.
What counts as spend
The report counts ordered value: purchase orders by their order date, with cancelled, rejected and void orders left out. It does not wait for the bill or the payment, because the decision to spend was made when the order was raised, and that is the decision a board is asking about. The range starts on 1 January of the current year unless you choose another.
Shillings and dollars are never added
An order is in the currency of the quotation behind it. The report shows one currency at a time: shillings first, with a currency picker that appears only when there are orders in more than one. The dozen dollar orders for caps and labels are a separate view in dollars. Adding them to shillings at today’s rate produces a number that is true for nobody, so the report does not do it.
Above the table sit five figures for the range and currency: the total ordered, the number of orders, the number of suppliers, the average days from order to first delivery, and the savings. Below them, seven views of the same orders:
| View | What it answers | Reads |
|---|---|---|
| By supplier | Who gets the money, and what share | Order totals, tax included |
| By category | What the money buys | Order lines, with quantities |
| By department | Which cost centre ordered it | Order totals |
| By requestor | Who asked for it | Order totals, and how many came through a requisition |
| By budget | Spent, committed and left per budget | Budgets live in the range |
| Cycle times | How long buying takes, per supplier | Requisition, order and first receipt dates |
| Negotiated savings | What tendering saved, and against what | Award decisions and competing bids |
The top five, as a share
By supplier lists every supplier with its orders, its ordered value and its share of the total, largest first. For the Namanve processor the first five rows answered the chair’s first question before the meeting: the sugar refinery, the preform maker, the carton printer, the fuel distributor and the cap importer took 68% of shilling spend between them. That is not a problem in itself. It is the number a board needs before it asks what happens if the preform maker’s line goes down for a fortnight.
By category reads the order lines rather than the order totals, because a category belongs to an item, not to an order: one order can carry sugar and cleaning chemicals. Categories are typed on the item, so “Packaging” and “packaging ” are folded into one rather than reported twice. Because line values and order totals are counted differently, the category total can differ from the supplier total by the tax and charges carried on the order itself.
By requestor credits an order to the person who wrote the requisition behind it, or to whoever raised the order where there was none, and counts how many of each person’s orders came through a requisition at all. A name with forty orders and none through a requisition is worth a conversation, whatever the amounts.
How long buying takes
The chair’s second question was about a spare part. Cycle times measure three legs per order: request to order, order to first receipt, and the whole journey from request to receipt, averaged per supplier and overall, with the median order-to-receipt beside the average so one lost shipment does not stand for a supplier’s year.
The important rule is what an average is allowed to count. An order with no requisition behind it has no first leg; an order with nothing received yet has no second. Each average is taken only over the orders that have that leg, and the report says how many that is. “Nine days, over 46 orders” and “nine days, over two” are not the same finding, and a report that hides the difference invites a decision on the second as if it were the first. For the processor, the spare-parts supplier’s order-to-receipt median was 23 days over eleven orders; request-to-order was another eight, almost all of it waiting for a quote.
An average that does not say how many orders it rests on is an anecdote in a table.
Savings, and against what
The third question is the one procurement teams most want to answer and most often answer badly, because a saving needs a baseline and the baseline is usually whatever makes the number large. The report uses two, and labels which one each row used:
Negotiated
- For a quotation request that ran bid rounds.
- The winner’s round-one total against the total awarded.
- Read from the award decision recorded when the award was made.
Competitive
- For every other order that came from a quotation request.
- The awarded quote against the average of the other bids in the same currency.
- A request with a single bid has no baseline and is left out, not shown as zero.
Two awards in the quarter
An award above the average of the other bids shows as a negative saving. That is not an error: it is the cost of choosing a supplier for something other than price, and the committee should see it.
How the bid rounds behind the negotiated figure work is covered in The Second Bid Round. The by-budget view reads the same spent, committed and left figures as the budget check on a requisition, described in A Budget That Warns and a Status That Refuses; budgets are kept in the base currency, so that view answers only in shillings.
Every view exports to CSV and PDF for the board pack, and the same figures are in the mobile app. Opening the report needs both the reports permission and the procurement view permission, so a buyer who cannot see reports does not see spend, and a report reader outside procurement does not either.
Three questions for your next finance committee
What share of our spend goes to our five largest suppliers?
What you will probably hear
I will need a few days to pull it.
How to read it
Then the answer is rebuilt every quarter and cannot be compared with the last one.
How many orders is that average delivery time based on?
What you will probably hear
All of them.
How to read it
Orders not yet received have no delivery time. An honest average counts only the ones that do, and says how many.
The tender saved how much, compared with what?
What you will probably hear
Compared with the budget.
How to read it
A budget is a plan, not a price. Ask for the first-round bid or the competing bids.
What AWRA OpsHub does today
- Spend by supplier, category, department and requestor, with each row’s share of the total, largest first.
- Spend against budgets, with spent, committed, remaining and percentage used.
- Cycle times per supplier, from request to order to first receipt, each average stating how many orders it counts, with the median beside it.
- Savings two ways, negotiated from bid rounds and competitive against the other bids, labelled per row.
- One currency at a time, never converted, with no currency picker for a business that buys in one.
- CSV and PDF export, the mobile app and the API reading the same figures.
More we can add to your workspace
- A converted total across currencies, shown beside the per-currency figures and labelled with the rate used. Commission it
- Spend measured on bills or payments as an alternative to ordered value. Commission it
- A managed category list for items, replacing free-text categories. Commission it
- An alert when one supplier’s share passes a limit you set. Commission it
- A month-by-month trend per supplier for the range. Commission it
Where we point you to a specialist
- Whether 68% with five suppliers is too concentrated depends on your market and your contracts. The report measures the share; the judgement about supply risk belongs to your procurement committee.
The converted all-currency total is the one most often requested by groups that buy in dollars and report in shillings.
From a quarterly report to a standing watch
The seven views, the cycle times, the savings and the exports are in place. These are the extensions that turn them into something the committee does not have to ask for.
Concentration alert
A note to the procurement manager when one supplier passes the share you set.
Supplier trend by month
Each supplier’s ordered value month by month, for spotting drift.
Managed categories
A fixed category list for items, so the category view stays tidy without cleaning.
Where this leaves you
Open the spend report a week before the committee, not the night before. The share by supplier answers concentration, the cycle-time medians with their order counts answer the delay, and the savings rows answer “compared with what” with a named baseline per award. Export the three views to PDF and the agenda is answered from the purchase orders themselves.
See procurement analytics
Spend by supplier, category, department and budget, cycle times and savings, in one currency at a time.
Explore procurement analyticsFrequently asked questions
Does procurement spend analytics count orders, bills or payments?
Ordered value: purchase orders by order date, with cancelled, rejected and void orders left out.
How are orders in different currencies handled?
One currency at a time. An order is in the currency of its quotation, and figures in different currencies are never added or converted. The currency picker appears only when there are orders in more than one.
How is a negotiated saving calculated?
For a quotation request that ran bid rounds, it is the winner’s round-one total less the awarded total. For other awards it is the average of the other bids in the same currency less the awarded quote, and a request with a single bid is left out.
Why can the category total differ from the supplier total?
Category reads the order lines, because a category belongs to an item. Supplier, department and requestor read the order total, which can include tax and charges carried on the order itself.
Who can open the spend report?
Someone holding both the reports permission and the procurement view permission. The same figures are available in the mobile app and as CSV and PDF exports.