Procurement Spend Analytics
See where purchasing money went (by supplier, category, department, requestor and budget), how long buying takes from request to delivery, and what competing bids and bid rounds saved. One view and one currency at a time, on the web and in the app.
Open Reports → System Reports and choose Procurement Spend Analytics under Procurement. It is also under Spend Analytics in the Procurement Related menu, and in the mobile app from the Procurement overview. You need both view reports and view procurement.
What Counts As Spend
- Spend is ordered value: purchase orders, dated by their order date. Cancelled, rejected and void orders are left out.
- The period starts on 1 January of this year until you change the dates.
- Supplier, department and requestor figures use the order total, tax included. The category view uses the order lines, because a category belongs to an item rather than to an order.
The Seven Views
Choose a View at the top. Every view shows the same headline figures for the period: Ordered, Purchase orders, Suppliers, Avg order to receipt and Savings.
| View | What it shows |
|---|---|
| By supplier | Orders, amount ordered and share of the total for each supplier, largest first. Each supplier opens its record. |
| By category | Line value per item category. Categories are the free-text category on each item, so Stationery and stationery are counted as one. Lines on items with no category show as Uncategorised. |
| By department | Amount ordered per department on the purchase order. |
| By requestor | The person who asked: the author of the requisition behind the order, or whoever raised the order when there was none. Via a requisition says how many of their orders came through one. |
| By budget | Every budget that overlaps the period, with its amount, spent, committed, remaining and % used, fullest first. |
| Cycle times | Days from request to order, from order to first receipt, and from request to receipt, per supplier and for all suppliers, with the median order-to-receipt time. |
| Negotiated savings | What each award saved and how it was measured (see below). |
Reading Cycle Times
Not every order has every step. An order raised without a requisition has no request-to-order time, and one with nothing received yet has no order-to-receipt time. Each average counts only the orders that have that step, so a supplier’s figure is never pulled down by orders that simply have not arrived. The Orders column shows how many orders each row covers. Receipt means the first stock check-in against the order.
How Savings Are Measured
- Negotiated: for an RFQ that ran bid rounds in the Sourcing Workbench, the winning supplier’s round-one total against the total awarded. The Basis column reads, for example, Round 1 vs round 3.
- Competitive: for any other order that came from an RFQ, the awarded quotation against the average of the other bids on that RFQ in the same currency. The Basis column says how many bids it was compared with.
- An RFQ with only one bid has nothing to compare against, so it is left out rather than shown as zero.
- An award above the average of the other bids shows as a negative saving. It is not hidden.
The total row splits the figure into negotiated and competitive.
One Currency At A Time
Each figure on the page is in a single currency. An order is in the currency of the quotation it came from, and an order with no currency counts as your base currency. If your orders in the period are in more than one currency, a Currency picker appears and the headline figures carry the currency code. Amounts in different currencies are never added together or converted. If every order is in one currency, there is no picker.
Budgets are kept in your base currency, so By budget answers only in that currency. In another currency it says Budgets are kept in your base currency and asks you to switch.
Exports, App And API
- CSV and PDF export the view, period and currency on screen. The PDF title names all three.
- The mobile app’s Spend Analytics screen offers the same seven views, dates and currency choice, with a chart of the top rows.
- The same figures are available from the API for your own tools.
If your workspace asks for step-up verification before exports, the CSV and PDF ask for your password or approval PIN first.
Common Issues
- A total looks low. Check the currency picker: orders in other currencies are in their own view, not added in.
- Spend does not match supplier bills. This report measures what was ordered, not what was billed or paid. Use the Procurement Reports for amounts paid and due.
- A category appears twice. The two spellings differ by more than capitals and spaces. Correct the category on the items.
- No savings shown. No award in the period had a second bid or a bid round to measure against.
Need help with this topic?