Planning & Gantt
Turn a list of tasks into a schedule you can defend: milestones, dependencies, a Gantt timeline, and an automatically computed critical path that shows what actually drives your finish date.
Open a project and choose Timeline to see the Gantt view. Every task with both a start and a due date is a bar, with dependency arrows, a thin baseline line once a baseline is set, a live Today line and your non-working days shaded. Milestones are diamonds on their dates. Use Day, Week and Month to zoom; a Table view below the chart lists the same tasks and dates, and tasks without both dates are listed under Unscheduled. Projects with more than 600 dated tasks show the first 600 by start date.
Re-Planning On The Gantt
- Drag a bar to move a task; its length is kept. Drag its right edge to change only the due date. Drag a milestone diamond to move the milestone.
- By keyboard: Tab to a bar, Left or Right moves it a day, Shift with Left or Right changes its due date, and Enter opens the task.
- Every move is saved straight away. A move that breaks a finish-to-start dependency is saved and flagged rather than refused. If the moved task now starts before a task it depends on finishes, move one of them yourself. If tasks that depend on it now start too early, choose Push successors later: each open successor moves later by exactly the days needed, keeping its length, down the chain. Nothing is pulled earlier, and done or cancelled tasks are reported, not moved.
- Moving a task needs the permission to edit tasks as well as project planning; moving a milestone needs project planning. Someone who can view the timeline but not re-plan it is told so under the chart. The mobile app shows a read-only timeline.
Milestones
Add milestones to mark the moments that matter — a beta, a go-live, a hand-off. Each has a due date and an open / met / missed status, shown on the project detail and along the timeline.
Task Dependencies
On any task, add a finish-to-start dependency — "this can't start until that finishes". The task page shows a Blocked by and Blocks view so the chain is explicit. The dependency graph is guarded: a link that would create a cycle, directly or transitively, is rejected before it is saved.
The Critical Path
AWRA runs the classic critical-path method over your dependencies — a topological order, a forward pass for earliest start/finish, a backward pass for latest, then slack per task. Tasks with zero slack form the critical path, highlighted in red on the timeline: delay one and the whole project slips.
| Term | Meaning |
|---|---|
| Early start / finish | The soonest a task can start/finish given its dependencies. |
| Late start / finish | The latest it can start/finish without delaying the project. |
| Slack | How long a task can slip before it moves the finish date. |
| Critical path | The zero-slack chain that determines the finish date. |
Baseline & Variance
Use Set baseline to snapshot the current plan. The timeline then shows a thin baseline line under each bar, and hovering a bar shows how many days late or early it is against the baseline, so slippage becomes visible instead of hidden. For who is over-allocated across projects, and the health of every project at once, see Capacity & Portfolio. See also Agile Delivery for an iteration-based cadence over the same tasks.
Need help with this topic?
Capture the module, record number, branch or warehouse, user, visible message, and what you expected to happen before contacting support.